Atakoy – Turkey
Process: Activated Sludge Plant
Duration of the project: 2016 - 2019
Client: ISKI, Istanbul Water and Sewerage Administration
The Ataköy water treatment plant is located in the south-western part of Istanbul city, near to Atatürk International Airport.
The scope of work includes the revamping of the existing plant that came in service in 2010 and the construction of a new WWTP having capacity 240,000 m3/d plus an MBR section sized for 20,000 m3/d. Total area for new construction is of 100,000 m2.
The contract is of EPC (Engineering, Procurement, Construction) type, and it is relevant to turn-key supply including civil works for a duration of works of 730 days.
1,000,000 inhabitants equivalent
- Rock trap
- Coarse screening 50 mm, fine screening at 10 mm and perforated screen 6 mm
- Aerated Degritting with grease removal
- Primary Clarification
- Bio P biological selector
- Anoxic/Denitrification basins
- Aerated/Nitrification basins
- Secondary Clarification
- Disinfection
- Thickening by flotation/thickener
- Anaerobic Digestion
- Sludge dewatering by centrifuges
- Sludge thermal drying with fluidified bed
Capacity: 20,000 m3/d
- Coarse screen 2 mm
- Drum screening at 1 mm
- Anoxic/Denitrification basins
- Aerated/Nitrification basins
- UF membranes 20 l/h m2 flux
- Disinfection
Related projects
Saudi Arabia
ZULUF Water Treatment Plant
Find out moreZULUF Water Treatment Plant
Saudi Arabia
#2 Lot of the Riachuelo system in Buenos Aires (Argentina)
Argentina
The #2 Lot of the Riachuelo system in Buenos Aires (Argentina) is an infrastructure and engineering project aimed at the reduction of organic pollution in the Rio de la Plata where the Riachuelo River, the most contaminated river in Argentina, flows.
Yenikapi - Turkey
ISTANBUL – TURKEY
Waste water are collected from Yenikapi area and after treatment are discharged to Marmara Sea. The Heatment process is based on “High Load Activated Sludge” type. The plant is located in a central ...
San Colombano - Florence
Italy
The waste Water treatment plant is located on the left bank of the river Arno and it is part of a large environmental project interesting an area around Florence of 200 hectares and serving eight municipalities.
Sokoto Potabilization Plant
Nigeria
Clariflocculation, filtration over rapid-gravity filters, disinfection with gaseous chlorine. The plant treats surface water from the Garonyo artificial basin and from the Rima river for the Sokoto Acqueduct.
Paracel water treatment package
Paraguay